Who is responsible for creating the Definition of Done if it is not an organizational standard?

Answer

The Scrum Team, including the Product Owner and Developers.

Explanation

If not set by the organization, the Scrum Team creates the Definition of Done collaboratively.

Last reviewed: October 2026

Reviewed by FirstInTest Editorial Team

Report an error

Related questions

What is the primary way the Product Owner communicates the product vision and goals to the Scrum Team and stakeholders?

View question →

What is the primary purpose of the Product Goal?

View question →

What is the Product Owner's role in the Daily Scrum?

View question →

How should the Product Owner handle technical debt?

View question →

A Product Owner is refining the Product Backlog and wants to ensure the items are ready for the upcoming Sprint. Which of the following best describes the level of detail needed for Product Backlog items at the top of the backlog?

View question →

During a Sprint, the Developers inform the Product Owner that they have discovered additional work needed to meet the Sprint Goal. What should the Product Owner do?

View question →

QuestionBack to list
FirstInTest

A world-class coach for every exam.

Product

CoursesVideosPricingNewsBlogFeedback

Company

About usFAQEditorial PolicyContact usFeedbackCommunityFor AI Assistants

Legal

Editorial PolicyTermsPrivacyRefunds