During a Sprint, the Developers inform the Product Owner that they have discovered additional work needed to meet the Sprint Goal. What should the Product Owner do?

Answer

Collaborate with the Developers to understand the impact and possibly adjust the Sprint Backlog.

Explanation

The Product Owner should work with the Developers to understand the new work and decide how to handle it, which may involve adjusting the Sprint Backlog while keeping the Sprint Goal in mind. The Sprint Backlog is owned by the Developers, but the Product Owner collaborates on scope.