The Scrum Team has started using “partial demos” to validate progress weekly, but they still hold a Sprint Review at the end with only a PowerPoint summary. What is the most accurate PSM I critique?

Answer

A Sprint Review must inspect the Sprint Goal with stakeholders, based on usable Increment, and include adaptation.

Explanation

Scrum expects stakeholders to inspect the Increment toward the Sprint Goal, and then adapt. Limiting to slides and not showing inspectable results undermines the empirical loop.