A Scrum Team decides to commit to a Sprint Goal that is “flexible” by allowing substantial scope changes to the Sprint Backlog every day. Which statement best reflects why this violates the intent of commitment?

Answer

Sprint Goals should remain stable for the duration of the Sprint to provide unity of purpose for the Developers.

Explanation

The Sprint Goal anchors inspection and adaptation during the Sprint; frequent re-negotiation indicates lack of true commitment. The Developers can adjust the plan, but the goal’s intent is not meant to be rewritten daily.