The project manager must decide whether a change request is “beneficial” when it improves a single KPI but increases cost and delays a dependent milestone. Which analysis approach is most consistent with integrated change control?

Answer

Evaluate trade-offs across scope, schedule, cost, quality, and stakeholder impact, using documented assessments to decide with the change control board.

Explanation

Integrated change control evaluates the full set of impacts rather than optimizing one metric. Trade-offs and stakeholder effects must be assessed and decided through governance.