Which statement best captures the relationship between Sprint Backlog, work plan, and the empirical inspection loop?
Answer
The Sprint Backlog is the Developers’ plan for realizing the Sprint Goal and can be updated during the Sprint
Explanation
Scrum defines the Sprint Backlog as the Developers’ forecast and evolving plan for the Sprint Goal. Updates enable empirical adjustment based on evidence.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
Passage: The Scrum Master observes that after Sprint Review feedback, the Product Owner produces a new roadmap and assigns work for the next sprint based on the roadmap’s expected scope. The team then stops refining the Product Backlog, claiming the roadmap items are now “locked.” During Sprint Planning, the Developers select items that exactly match the expected scope, even though early indicators during the sprint suggest that some items may be less valuable. The Sprint Goal ends up becoming a paraphrase of the roadmap’s deliverables rather than a concise objective for value.
View question →
A Development Team proposes adding new tasks mid-Sprint that change the definition of ‘Done’ after work has started. What is the best Scrum-consistent approach?
View question →
A team’s Daily Scrum has become a status meeting to report progress to external stakeholders. What is the most accurate implication?
View question →
In Scrum, which situation most strongly indicates the organization is still effectively treating the Product Backlog as a delivery plan rather than an ordered commitment?
View question →
Passage: During a sprint, the Product Owner receives new customer evidence suggesting that the next best value is now a different feature than the one selected at the start of the sprint. The Developers argue that they already committed to the Sprint Goal and therefore cannot change their work focus until the sprint ends. The Scrum Master notices that while the Product Backlog is ordered for value, the team is also using the sprint as a “frozen plan” to avoid churn. At the Daily Scrum, progress is discussed only against the original selected items, not against the Sprint Goal.
View question →
A Scrum Team frequently negotiates Sprint commitments with stakeholders after Sprint Planning, effectively treating the Sprint Goal as a variable to be re-traded mid-Sprint. Which situation best reflects a violation of PSM I principles?
View question →