Which scenario best illustrates the Scrum Master’s duty regarding event effectiveness when stakeholders request skipping Sprint Review to “save time,” arguing that production metrics suffice?
Answer
The Scrum Master should ensure the Sprint Review occurs to enable outcome inspection and backlog adaptation, while coaching stakeholders on effective participation and evidence-based decisions.
Explanation
Skipping a required Scrum event removes essential inspect-and-adapt opportunities; the Scrum Master coaches for effective engagement and evidence rather than replacing the purpose.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
In a Sprint Review, the team’s output is largely not demonstrated because it is “not ready,” but the Product Owner still claims progress. Which interpretation aligns best with Scrum?
View question →
A Scrum Team notices that stakeholders increasingly request changes mid-Sprint that materially impact Sprint Goal achievement. What is the most appropriate Scrum-consistent response?
View question →
A Scrum Team’s Definition of Done is overly broad and allows merging incomplete work as long as “tests exist.” What is the most Scrum-accurate improvement path?
View question →
In a PSM I context, which statement best explains how Scrum’s empirical process control constrains the Development process when forecasts about delivery are unstable?
View question →
Multiple teams share a common Definition of Done but use different criteria for “ready.” In practice, integration fails frequently near Sprint end. What is the most advanced PSM I-aligned corrective action?
View question →
A Product Owner is repeatedly asked to prioritize during the Sprint, but the work is already committed toward the Sprint Goal. What is the most correct Scrum stance?
View question →