Which scenario best illustrates the Scrum Master’s duty regarding event effectiveness when stakeholders request skipping Sprint Review to “save time,” arguing that production metrics suffice?

Answer

The Scrum Master should ensure the Sprint Review occurs to enable outcome inspection and backlog adaptation, while coaching stakeholders on effective participation and evidence-based decisions.

Explanation

Skipping a required Scrum event removes essential inspect-and-adapt opportunities; the Scrum Master coaches for effective engagement and evidence rather than replacing the purpose.