Which outcome best demonstrates “no surplus work” during a Sprint under Scrum?
Answer
The team does not add extra work beyond what supports the Sprint Goal
Explanation
Scrum emphasizes focusing on achieving the Sprint Goal rather than maximizing volume. Avoiding unnecessary work reduces waste and improves predictability.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
A developer claims they can safely skip code reviews because the team has a strong backlog. Which alternative is more aligned with PSD practices?
View question →
A team uses a shared codebase where build failures occur once a day. Which practice most directly supports a “fast feedback loop” in PSD?
View question →
What is the primary purpose of the Sprint Review for the Scrum Team?
View question →
Which statement best describes the purpose of the Definition of Done (DoD)?
View question →
A Development Team frequently changes its plan after each daily stand-up. Which action most improves predictability without breaking Scrum?
View question →
During Sprint execution, the team discovers technical debt that prevents meeting the Sprint Goal unless addressed now. What is the best Scrum-consistent response?
View question →