Which concept is primarily responsible for enabling empirical process control in Scrum?

Answer

Transparent inspection and adaptation based on data

Explanation

Empiricism in Scrum relies on transparency so inspection is meaningful and adaptation is taken based on observed reality.

Last reviewed: October 2026

Reviewed by FirstInTest Editorial Team

Report an error

Related questions

Which situation is most aligned with the role of a Scrum Master?

View question →

During Daily Scrum, a developer spends most of the time explaining technical details of a specific task. What is the best Scrum response?

View question →

Which statement best describes the purpose of the Product Backlog?

View question →

A Development Team finds at the start of a Sprint that some work was already done. What is the best Scrum-consistent action?

View question →

A Scrum Team’s Definition of Done is unclear. What is the best next step?

View question →

A team is debating whether an item should move from “In Progress” to “Done.” The team’s Definition of Done is: 'The feature is usable, meets acceptance criteria, passes automated tests, and is documented.' Which action is most appropriate?

View question →

QuestionBack to list
FirstInTest

A world-class coach for every exam.

Product

CoursesVideosPricingNewsBlogFeedback

Company

About usFAQEditorial PolicyContact usFeedbackCommunityFor AI Assistants

Legal

Editorial PolicyTermsPrivacyRefunds