Which artifact is used to represent the work needed to achieve the Product Goal?

Answer

Product Backlog

Explanation

The Product Backlog contains the ordered items needed to achieve the Product Goal. The Sprint Backlog is a forecast for the Sprint.

Last reviewed: October 2026

Reviewed by FirstInTest Editorial Team

Report an error

Related questions

In Scrum, what does the Daily Scrum primarily help the Developers do?

View question →

Which event in Scrum is intended to inspect progress toward the Sprint Goal and adapt the plan if needed?

View question →

Who is responsible for ordering the Product Backlog?

View question →

The Product Owner wants to improve outcomes over time. They do not try to dictate every solution detail, but instead manage a long-term direction for the product and keep the Product Backlog ordered for value. Developers are expected to collaborate to build an Increment that meets agreed quality expectations. The Scrum Master supports the team by removing blockers and coaching Scrum practices. Which artifact provides the agreed quality expectations for the Increment?

View question →

What is the purpose of the Sprint Goal?

View question →

During a Sprint, Developers decide how work will be performed. What is this responsibility called?

View question →

QuestionBack to list
FirstInTest

A world-class coach for every exam.

Product

CoursesVideosPricingNewsBlogFeedback

Company

About usFAQEditorial PolicyContact usFeedbackCommunityFor AI Assistants

Legal

Editorial PolicyTermsPrivacyRefunds