Which activity is most directly associated with the Product Owner’s responsibility for Product Backlog management?
Answer
Ordering the Product Backlog to reflect value and return on investment
Explanation
Ordering and managing the Product Backlog to maximize value is a core Product Owner responsibility.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
Which statement correctly describes the purpose of the Daily Scrum?
View question →
During a Sprint, the Scrum Master sees the Developers preparing to change Sprint Goal commitments after a new request arrives. What is the most appropriate Scrum-aligned response?
View question →
The Product Owner claims that because stakeholders requested a new feature, the team should simply add it to the current Sprint without affecting anything else. Based on Scrum, what is the most accurate implication?
View question →
In Scrum, which statement best captures the purpose of the Product Backlog?
View question →
What best explains why the Developers own the Sprint Backlog?
View question →
What is the key timebox outcome of the Sprint Review?
View question →