During Sprint Review, a stakeholder asks to see interim metrics and requests additional work be pulled into the Sprint because “the data looks promising.” What is the correct Scrum response?

Answer

Use the Sprint Review to inspect the increment and adapt the Product Backlog; new work is considered for future Sprints

Explanation

Sprint Review is for inspecting the increment and adapting the Product Backlog. Scope changes in the middle of a Sprint are not the default and should not be treated as immediate contractual commitments.