During Sprint Planning, the Product Owner presents the top Product Backlog items. What is the expected outcome of this event?
Answer
A Sprint Goal and a Sprint Backlog that the Developers can commit to.
Explanation
Sprint Planning results in a Sprint Goal and a Sprint Backlog. The Developers create the Sprint Backlog, and the Product Owner ensures the items align with the Product Goal.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
Which statement best describes the relationship between the Product Goal and the Sprint Goal?
View question →
A Product Owner is working with the Developers to refine the Product Backlog. Which of the following is a key benefit of regular refinement?
View question →
A Product Owner is preparing for the upcoming Sprint and wants to ensure the Product Backlog is in good shape. Which of the following best describes the appropriate level of detail for Product Backlog items?
View question →
During a Sprint, the Developers discover that they need to change their approach to meet the Sprint Goal. Who is responsible for making this decision?
View question →
A Product Owner is working with the Scrum Team to define the Product Goal. Which of the following best describes the Product Goal?
View question →
A Product Owner wants to maximize the value delivered by the Scrum Team. Which action is most aligned with this responsibility?
View question →