During Sprint Planning, the Product Owner presents the top Product Backlog items. What is the expected outcome of this event?

Answer

A Sprint Goal and a Sprint Backlog that the Developers can commit to.

Explanation

Sprint Planning results in a Sprint Goal and a Sprint Backlog. The Developers create the Sprint Backlog, and the Product Owner ensures the items align with the Product Goal.