During a Sprint, a Developer learns that a previously selected plan for a PBIs implementation is no longer suitable. What is the best action consistent with Scrum?

Answer

Modify the implementation approach while keeping the Sprint Goal in focus

Explanation

Scrum allows Developers to adapt their work as long as the Sprint Goal remains the focus and the Sprint Backlog forecast is updated as needed.