After a product increment is delivered, the Product Owner wants to incorporate learning from actual usage into future work. What is an effective next step?
Answer
Reorder the Product Backlog based on validated learning and update forecast
Explanation
Scrum is empirical: insights from the increment should inform backlog ordering and future work selection. A forecast update helps reflect new understanding.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
In Scrum, which are acceptable ways for the Product Owner to increase product value?
View question →
During a sprint, the Development Team identifies a new opportunity that could be addressed without reducing the Sprint Goal. Who decides whether to include it?
View question →
A team consistently finishes items but customers report the product does not solve their real problem. What is most likely the issue in Scrum terms?
View question →
Which example best illustrates the Product Owner’s role in ensuring transparency of value?
View question →
A Product Owner receives conflicting feedback from two customer groups about feature priority. Which action best supports an empirical approach?
View question →
Select the set of statements that are consistent with Product Owner accountability for acceptance of work.
View question →