A team is working on the same Sprint Backlog item for three days with no measurable progress. What is the best Scrum-aligned action?
Answer
Use Daily Scrum inspection to adapt the plan toward the Sprint Goal, possibly rework the approach or refine understanding
Explanation
Daily Scrum provides a frequent inspection and adaptation loop for the plan. The team should adjust its approach to stay aligned with the Sprint Goal.
Last reviewed: October 2026
Reviewed by FirstInTest Editorial Team
Related questions
During a Daily Scrum, what is the primary purpose for the Developers?
View question →
A team uses a “Definition of Done” that applies only to coding, not testing or documentation. What risk does this create and what is the best Scrum-aligned remedy?
View question →
Which artifacts are used to maximize transparency of key information in Scrum?
View question →
A Scrum Master hears that the team wants to skip the Sprint Review because stakeholders are busy. A stakeholder asks for evidence of progress and outcomes anyway. What is the most Scrum-consistent response?
View question →
In Scrum, which statement best describes how the Sprint Goal relates to the work of the Developers?
View question →
Which statement is the best description of Scrum Events?
View question →