A Scrum Master observes that the Development Team regularly pulls tasks from the Product Backlog directly into the Sprint Backlog without creating a Sprint Plan and without defining how the work will achieve the Sprint Goal. Which assessment is most aligned with PSM I?

Answer

This is harmful because it bypasses Sprint planning and the purpose of the Sprint Goal and forecast

Explanation

Sprint planning is required to produce the Sprint Goal and a plan for achieving it. Copying backlog items into the Sprint Backlog without planning reduces transparency and adaptability.