CUET UGQuantitative AptitudeMultipleCorrect
Ram, Shyam and Hari can complete a work in 20, 25 and 30 days, respectively. Consider the following statements: (A) Ram and Shyam together will complete the work in $11 \frac{1}{9}$ days. (B) Shyam and Hari together will complete the work in 14 days. Choose the correct answer from the options given below: